Budget Overall Overview

Screen #1 – Setting the approved budget

Budgets in Epicflow let you set aside a number of work hours and track how many of them your tasks use. There are two kinds:

 

  • Approved budget – the total hours approved for the whole project. You compare it with the hours actually planned.
  • Budget tasks – a reserve of hours for one group of people inside one part of the project, such as a module. Tasks for that group use up these hours automatically.

For budgets assigned to teams, see Team budget.

Set the project’s approved budget

  1. In Pipeline, double-click the project name. The Project card opens.
  2. Open the Effort tab.
  3. Click the number next to Approved budget, type the approved hours and press Enter.
  4. Click Save at the bottom of the card (Screen #1).

Over/under budget now shows the difference between Approved budget plus Approved changes and Total planned. A positive number means hours are still free. A negative number (shown in red) means more hours are planned than approved.

Note

The Effort tab shows the budget in work hours. The project’s budget in money is shown on the Financial Overview tab.

Create a budget task

  1. Open the project and add a task inside the summary (module) the budget is for.
  2. In the Assignee column, choose the group whose hours you are budgeting, e.g. Engineering (required).
  3. In the Total column, enter the budgeted hours (required).
  4. Open the task card with the card icon next to the task name.
  5. Under Attributes, click + (or + Add attribute) and choose Budget (required).
  6. Click anywhere outside the list, then click Save (Screen #2).

The card title changes from Task to Budget and the task gets a budget icon. The Assi… column shows Auto.

To split a budget between specific people, see Budget distribution.

Screen #2 – Turning a task into a budget task

Tip: no Attributes field on the card?

Click the gear icon at the top of the card and tick Attributes. See Attributes.

Note

You may see CP, CP alt or 90% CP attributes on tasks. Epicflow sets them automatically to mark the critical path – leave them as they are. See Critical Path in Epicflow: CP, CP alt and 90% CP.

Show which budget a task uses

  1. Open any task card.
  2. Click the gear icon at the top of the card.
  3. Tick Related Budgets (Screen #3).

The task card now shows the budget the task uses, or None. For more examples, see Related Budgets and Tasks.

Screen #3 – Turning on the Related Budgets field

How tasks use a budget

You don’t link tasks to a budget by hand. A task uses a budget automatically when all of these are true:

  • the task is in the same summary as the budget task, or in a summary below it;
  • the task is assigned to the budget’s group, or to a person from that group;
  • if the budget has a phase, the task has the same phase.

The task card then shows the budget under Related budgets (Screen #4).

Screen #4 – A task that uses Budget Module A

A task assigned to a different group does not use the budget. Its hours are added to the project total (Screen #5).

Screen #5 – A task from another group has no related budget

Budgets and phases

  • A budget without a phase counts all tasks, whatever their phase.
  • A budget with a phase counts only tasks in that same phase. Tasks without a phase, or in a different phase, do not use it (Screen #6).


Screen #6 – A budget in the Design phase counts only Design tasks

Read the budget numbers

The top of a budget card shows four numbers (Screen #7):

  • Spent – hours already logged on tasks that use this budget.
  • Rem. Plan. – remaining hours on tasks that use this budget.
  • Unplan. – budget hours not yet given to any task.
  • Total – the budget size.

When you add or change a task that uses the budget, Rem. Plan. goes up and Unplan. goes down by the same amount.


Screen #7 – A 15-hour task uses part of a 20-hour budget

To see all budget tasks and the tasks that use them in one list, see Working with the budgets.

Budgets inside budgets

You can place a smaller budget inside a summary that already has a budget, e.g. Budget Module A.2.1 inside Module A.2. The smaller budget uses hours from the bigger one in the same way a task does (Screen #8).

  • An empty smaller budget still reserves all of its hours in the bigger budget.
  • Tasks inside the smaller budget’s summary use the smaller budget first.

Screen #8 – Budget Module A: 60 hours reserved by Budget Module A.2 plus 10 hours from Task 1

When a budget runs out

If tasks need more hours than the budget has, the budget is not extended (Screen #9):

  • the budget’s stage changes to Overrun;
  • a red $ icon appears next to the budget name;
  • Unplan. becomes negative, e.g. −5;
  • the extra hours are counted against the next budget up, if there is one.

To fix an overrun, increase the budget’s Total, or reduce the hours on its tasks.

Screen #9 – A 20-hour budget with 25 planned hours is in Overrun

Who can work with budgets

An administrator sets this in Settings → Roles & Permissions (Screens #10 and #11):

  • Task, Summaries and Milestones → Create & Delete Budget Tasks – create and delete budget tasks.
  • Task card fields → Item Attributes – must be Manage to add the Budget attribute.
  • Task card fields → Related Budgets – View or No Access.
  • Project permissions → Project approved budget – No Access, View or Manage.


Screen #10 – Budget task permission


Screen #11 – Approved budget permission

Good to know

People tend to use up all the hours they see available (Parkinson’s Law). To avoid this, set Related Budgets to No Access for the people doing the work, and use budgets only for planning and control.

If it doesn’t work

  • Budget is not in the attribute list: make sure the role has Item Attributes set to Manage.
  • A task doesn’t use the budget:
    • check that the task’s assignee belongs to the budget’s group;
    • check that the task is in the budget’s summary or below it;
    • if the budget has a phase, check that the task is in the same phase.
  • Changes on the card disappear: click Save in the “Save all changes?” bar at the bottom of the card.

Still stuck? Contact us at support@epicflow.com.

Current limitations

  • Overruns are not covered automatically. A budget that runs out is not extended. The extra hours show as Overrun and count against the parent budget.
  • Approved changes can’t be edited on the Project card.
  • Phases linked to the project start or end can break Project editing. Creating a phase with “Link phase start to project start” or “Link phase end to project end” can stop the project from opening. Set fixed start and due dates for phases instead.
Updated on November 10, 2026